Let's assume F1= 561+7.92P1+0001562P1*P1
F2= 310+7.85P2+0.00194P2*P2
F3=78+7.97P3+0.00482P3*P3
Total load demand=850MW
P1=400MW
P2=300MW
P3=150MW
Ploss=0.00003P1*P1+0.00009P2*P2+0.00012P3*P3